Upper Horfield Primary School, Bristol
Installation of new 828m² 3G artificial football pitch
MJ Abbott secured the project following a tender process with Bristol City Council's main contractor, MJ Church (Plant) Ltd.
The project comprised the construction of a single 3G artificial football pitch in accordance with the specification produced by Bristol City Council.
MJ Abbott carried out the following scope of works:
- Trim and grade sub-base provided by the main contractor, MJ Church
- Import and spread 50mm depth of dynamic stone regulating layer
- Installation of new 40mm depth synthetic carpet complete with sand and rubber infill
- Lines cut in as required.
MJ Abbott continue to provide maintenance support for the new pitch.