Completed walled garden, drive and Golpla areas
Completed walled garden, drive and Golpla areas
Completed walled garden, drive and Golpla areas
View from ha-ha between main buildings, prior to commencing landscaping works
View of first building with one of the large subsoil heaps which required to be incorporated into the landscaping
View from garage up towards main building, prior to shaping and driveway works
Area between buildings, prior to commencing landscaping works
View through ha-ha prior to commencing landscaping works
View towards rear building, prior to shaping works
Existing access prior to commencing landscaping works
Construction of new driveway over site access route, and shaping of surrounds
View between buildings following shaping, topsoil re-spread and tree planting prior to cultivation and seeding
View from ha-ha following construction works, during stone raking prior to stone picking and final cultivation and seeding
View through ha-ha following re-shaping and topsoil re-spread works
View towards rear building, following shaping and topsoil re-spread works
View down towards garage past main building, following shaping and topsoil re-spread
Walled garden, drive and Golpla sub-base under construction
 
 

Private Client, Hampshire

Landscaping works at new private residence

MJ Abbott Limited were approached by Willerby Landscapes to assist with the specialist earthworks, shaping and re-soiling to the grounds of a new private house near Petersfield, Hampshire.

The situation we faced was that the site had a shortfall of the topsoil required to complete the project, and a large surplus quantity of subsoil to be disposed of. All parties wished to minimise import and export of materials to and from site, so a viable solution needed to be found.

We worked closely with Willerby Landscapes, under the guidance of soil and landscape consultants Tim O’Hare Associates, to find the best solution to this problem. The proposed method, which we successfully implemented, was to strip and store the required topsoil from an adjacent field owned by the client which had a very good depth of existing topsoil, albeit very stony.

The existing vegetation was shallow rotovated and stripped prior to the remaining clean topsoil being stripped to its full depth and stored in a sealed heap on site, prior to the area receiving the surplus subsoil. This surplus subsoil was pushed out with our D6 bulldozer over a large area to allow for the spoil to follow the existing contours, and shaped to blend in smoothly with the surrounding features so that the newly shaped area looks entirely natural.

The surrounds of the buildings were softly contoured to blend in more naturally with the surrounding landscapes, and the new ha-ha was softened to improve the look of the site.

The stripped topsoil was then taken from the stockpile to the newly shaped areas and building surrounds, and spread to approximately 150mm depth. The previously stripped vegetation was then spread to the subsoil field area at 50mm depth prior to the remaining topsoil being spread at approximately 100mm depth.

While on site we installed drainage to the new tree pits, and created a turfed formal area with Golpla grass reinforcement for vehicle access.

We worked closely with Willerby Landscapes on the installation of the new trees, the new access driveway and the Golpla area. The remaining working areas were cultivated, stone picked and grade rolled prior to seeding with a low maintenance Pro Master 25 seed mix from DLF.

Follow us on Facebook Follow us on Twitter See our videos on You Tube Find us on LinkedIn